Authorities in Nepal have ordered a daily five-hour closure on a section of the Prithvi Highway beginning Saturday, November 21, so crews can clear dangerous rock and soil from the hillside at Ghoptebhir.

The Chitwan District Administration Office directed that vehicles be stopped from 11 a.m. until 4 p.m. each day on the affected Nagdhunga–Muglin corridor. The order remains in effect until further notice, according to reports by ABC Nepal TV and Kantipur.

The planned interruption follows repeated dry landslides that have disrupted movement on the corridor. The work is intended to remove unstable material above the road, rather than simply reopen lanes after debris has already fallen. Authorities have not announced a firm completion date.

ABC Nepal TV reported that traffic police identified holding points for vehicles approaching the work zone. Traffic coming from Narayangadh is to be stopped at Jugedi and Aaptari, vehicles from Pokhara at Aabukhaireni, and traffic from Kathmandu at Ramailo Danda. The restrictions apply to all vehicle types during the daily work window.

The road is an important link for passengers and freight moving between Kathmandu and western and central parts of Nepal. A predictable closure period allows workers to address the slope while keeping vehicles away from the immediate hazard. It also means travellers and transport operators must adjust departure times, particularly when a journey would otherwise reach the affected section around midday.

The Ghoptebhir section has experienced successive landslides in recent weeks, prompting repeated clearance operations. The administration has not provided an end date for the five-hour daily restrictions. Road users should consult current police and road authority notices before travelling because conditions and closure arrangements can change.